Iqaluit collector-road study must cost all three route options before City selects preferred alignment

ᓇᐃᓈᕐᓗᒍ

A City of Iqaluit addendum requires consultants bidding on the Core Area collector-road preliminary-design study to develop and cost all three alignment options to a comparable Class 2 estimate level. The clarification is meant to help the City decide which route offers the best value. The proposal call closed Sept. 9; no consultant award, route selection or construction approval has been posted. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

Share this briefingFacebookEmail

ᖃᓄᐃᓐᓂᖅᑲᑦ

The City issued Addendum 3 to 2026-RFP-016, its procurement for preliminary design of a new Core Area collector road. The addendum says all three alignment options—not only the preferred route—must be developed far enough to support Association for the Advancement of Cost Engineering Class 2 estimates. It says the estimates are intended to let the City make an informed best-value decision on the alignment. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

The City also directs bidders to forecast future traffic at four locations: Niaqunngusiariaq Road at Kangiq and Iniq; Kangiq and Iniq at Nunavut Drive; the proposed Links 2, 6, 7 and 8 intersection on Inuit-owned land; and Link 8 at Sivumugiaq Street. The addendum says no additional future development areas are required in the analysis. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

ᓱᒻᒪᑦ ᐱᒻᒪᕆᐅᒻᒪᖔᖅ

The planned road is intended to connect the Kangiq and Iniq Drive area to Sivumugiaq Street and support future development west of the Inuit-owned lands. The original RFP identifies Qikiqtani Inuit Association and its development corporation, Akiuq Corporation, as primary stakeholders because of planned integrated development on Inuit-owned and municipal lands. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

Requiring comparable estimates for every route gives the City a clearer basis to weigh construction costs alongside traffic, utilities, drainage, terrain and effects on nearby properties before choosing a preferred alignment.

ᖃᓅᓂᐊᓕᖅᑲᓕ

The City’s tender page lists the proposal deadline as Sept. 9, 2026 at 3 p.m. EST. The RFP anticipated evaluation by Sept. 23, a notice of contract award by Sept. 30 and a project kickoff in October, but those are estimated procurement milestones, not confirmed decisions. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

If a consultant is hired, the RFP anticipates preliminary design work through March 2027. The work would inform a later detailed-design phase; it does not authorize road construction. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

ᐱᒻᒪᕆᐅᔪᑦ ᖃᐅᔨᒪᔭᐅᒋᐊᓖᑦ

The addendum says a separate wind-and-snow analysis report is not required at this design stage. It also adds four background records to the project page: fuel-pipeline road-crossing as-built drawings, fuel-systems mapping, the City’s master drainage plan and an Iqaluit High School intersection feasibility study. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

The original RFP calls for three road and intersection options, stakeholder engagement, a high-level geotechnical investigation and a final concept sketch for the preferred option. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

Report an ErrorReviewed and approved for publication.
Verified community discussion

Comments

0 approved comments. Every comment is reviewed before appearing.

Real Facebook names
Start a useful, accountable discussion.

Comments appear here after identity verification and News Desk review.