Monday, September 28, 2026ᐃᖃᓗᓐᓃᑦᑐᑦ. ᓄᓇᕗᒻᒥ ᑕᑯᓐᓇᓂᖅᓴᐅᔪᑦ.
ᓴᖅᑭᖅᑕᐅᓯᒪᔪᑦ ᓄᓇᕗᒻᒥᐅᑕᕐᓄᑦ
ᐃᖃᓗᐃᑦ2.6°CLight RainWind SE 37 km/hFull forecast & boaters report →
Inuktitut navigation is available.

Stories are shown in English while Inuktitut story translation is paused.

Federal release details $2.94M in Nunavut clean-energy funding, with projects at mixed stages

ᓇᐃᓈᕐᓗᒍ

A July 29 federal backgrounder identifies $2,939,304 in funding for five Nunavut-specific clean-energy and related projects. The records show two projects still moving toward installation or construction planning—solar at Resolute Bay’s municipal garage and engineering for an Arviat hybrid microgrid—while the Chesterfield Inlet solar array, Cambridge Bay carbon analysis and Kivalliq wind-measurement work are described as completed. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

Share this briefingFacebookEmail

ᖃᓄᐃᓐᓂᖅᑲᑦ

Natural Resources Canada announced nearly $7 million for eight projects across the three territories. Its project backgrounder assigns $260,000 to the Municipality of Resolute Bay for a planned 15-kilowatt solar system on its municipal garage; $410,625 to Kivalliq Alternative Energy Ltd. for front-end engineering and design of an Arviat hybrid renewable-energy system; $729,434 to the Hamlet of Chesterfield Inlet for a 134-kilowatt rink-roof solar array; $99,000 to the Kitikmeot Heritage Society for embodied-carbon analysis of Cambridge Bay’s planned Kuugalak cultural research campus; and $1,440,245 to Nunasi Corporation for wind-resource work in Baker Lake, Whale Cove and Chesterfield Inlet. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

ᓱᒻᒪᑦ ᐱᒻᒪᕆᐅᒻᒪᖔᖅ

The funding supports diesel-reduction and energy-planning work in several communities, but it does not mean that all five projects are newly starting or will immediately change local power supply. The federal record says the Resolute Bay system will be installed and the Arviat project will complete engineering needed before procurement and construction. It describes the Chesterfield Inlet solar installation, Kuugalak analysis and Kivalliq wind assessment as completed work. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

ᖃᓅᓂᐊᓕᖅᑲᓕ

Resolute Bay’s planned garage solar project and Arviat’s engineering study are the active implementation items identified in the release. The federal document gives no construction date, procurement date, generation forecast or projected diesel savings for either project. Nunasi’s completed wind assessment is said to have enabled Baker Lake to enter construction planning and helped assess feasibility in Whale Cove and Chesterfield Inlet; it does not announce construction approval for those communities. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

ᐱᒻᒪᕆᐅᔪᑦ ᖃᐅᔨᒪᔭᐅᒋᐊᓖᑦ

The $2.94-million Nunavut total excludes a separate $2,807,398 Yukon University project that is based in Whitehorse but includes northern grid modelling, outreach and training intended to support community-led renewable generation in Yukon, the Northwest Territories and Nunavut. The July 29 announcement is later than Atiilu’s June 22 coverage of a separate $17.2-million federal Nunavut clean-energy package. ᓇᑭᓐᖔᖅᓯᒪᓂᖏᑦ

Report an ErrorReviewed and approved for publication.
Verified community discussion

Comments

0 approved comments. Every comment is reviewed before appearing.

Real Facebook names
Start a useful, accountable discussion.

Comments appear here after identity verification and News Desk review.